Construction of the two-story, 11,947 SF medical clinic included 20 exam rooms, three nurse stations, medical records room, full pharmacy, two reception areas (1st & 2nd floor), several office and support areas and a break area with an exterior terrace. The buildings exterior consists of a stucco finish with a decorative stone veneer and cementitious tile roof. An electrical traction elevator service both floors.
The Vista Community Clinic was constructed to LEED Silver & OSHPD specifications.
On this project we faced numerous challenges causing some delays. The major delays were not being able to get Permitted drawings from the City until 8/19/08 and per the original schedule we were to have these by 6/12/08. The other major delay we encountered was Rain. We had 2 weeks of Rain delays on this project during the framing and offsite improvement stages. Fortunately we were able to make days up with weekend work, long hours and hit the Clinics anticipated Grand Opening in July. The official Grand Opening to the public was on August 27th and was a complete success!
Project Schedule: 6/9/2008 - 7/8/2009
Final Construction Cost: $3,770,248.00
Notable Comments:
“Erickson-Hall’s entire team did a fabulous job! They were committed, professional and knew how to problem solve.”
Barbara Mannino
CEO, Vista Community Clinic